Record point cloud asynchronously

Records a point cloud with the currently active camera. Fixed cameras can therefore be triggered in the background.

The camera only triggers the recording(s) with this task. In contrast to the Record point cloud task, the recording is executed in parallel to the sequence. This means, for example, that robot movements can take place during the recording. If the camera data is required in a subsequent task, the system waits for this task to be completed.

The point cloud is not yet visible in the visualization. As soon as an object search (or handle search) has been carried out, the point cloud and objects found are inserted into the visualization.

Hint

It is not permitted to record point clouds in the process while a recording has not yet been completed. Such a situation leads to a program error. Therefore, when using asynchronous recordings, ensure that the subsequent recording is started at the earliest after the previous one has been completed.

Hint

If a sequence is stopped during an asynchronous recording, the recording will still be completed. Do not resume the sequence until this recording has been completed at the earliest.

Variablen

Name

Typ

Description

Delay

Integer

Waiting time in [ms] before the recording is triggered. Application example: Before the recording is triggered, the robot should be moved out of the field of view of a fixed camera.